Work will begin on March 4th and
continue until mid-May for the addition
of an auxiliary lane of traffic between
25th and 37th street. On-ramps at 35th
street will be closed the week of
February to complete work on lane
markings. The work start times are
dependent weather conditions. The work
will link the auxiliary lane at 35th
street with the lane in the Marquette
Interchange that ends at 25th street
under the current configuration. When
work is completed there will be three
westbound lanes and the auxiliary lane
connecting the Marquette Interchange
with the Stadium Interchange.
The work scheduled for this spring will
restore the second lane for I-794
westbound while maintaining the
improvements along I-43 southbound to
I-94 westbound. The work that took place
in spring 2012 improved the traffic
backups along I-43 but resulted in
unacceptable delays along I-794.
There will be a single lane closure
along I-94 westbound beginning on March
4th and running until mid-April.
Additional off-peak, overnight and
weekend work will continue until
mid-May. Eastbound traffic will see some
impacts due to median work that is
required. There will be no lane closures
eastbound.
Schedule and closure listings are
tentative and weather dependent. Please
check 511.wi.gov for up to date
information. Further project information
is available at
http://projects.511wi.gov/web/i-794-project.