Breaking News

  • Updated

WAUKESHA — Due to the west side pump station consolidation project, Madison Street between Fiddlers Creek Drive and Howell Oaks Road will be closed to thru traffic beginning Monday. It is anticipated the closure will last one week.

  • Updated

WASHINGTON COUNTY — The Wisconsin Department of Transportation is notifying motorists of an upcoming short-term closure of Highway 175.On Monday, crews will begin repairs on a roadway structure over a small creek between Pioneer Road and Pleasant Hill Road. Work is scheduled to be complete b… Read more

  • Updated

MUSKEGO — The Waukesha County Public Works Department will begin construction on County Highway Y (Racine Avenue) at the Pilak Creek Tributary to replace the culvert structure in Muskego on Monday, Sept. 28.The project is just south of Pioneer Drive and will continue through November.During … Read more

WAUKESHA, WI – Waukesha County Public Works is set to replace the culvert structure on County Highway Y at Pilak Creek Tributary in the City of Muskego. The project is located on CTH Y just south of Pioneer Drive. Construction is scheduled to begin on September 28, 2020 and to continue throu… Read more

WEST BEND — Crack and joint sealing work will be performed in the city through the following street segments beginning Monday, Sept. 21, until approximately Oct. 9.Project dates may be adjusted due to weather conditions or other circumstances.■ 5th Avenue: Maple Street to Oak Street■ 6th Ave… Read more

  • Updated

MADISON —The Wisconsin Department of Transportation is notifying motorists of upcoming temporary daytime closures of the County Q (County Line Road) entrance ramp to Interstate 41 southbound in Menomonee Falls. A right lane closure will also be in effect along I-41 southbound just north of C… Read more

  • Updated

WEST BEND — Minimal thru traffic will be allowed on Schmidt Road between Creek Road and Barton Avenue starting Tuesday until approximately Oct. 2 for pavement reconstruction. Project dates may be adjusted due to weather conditions or other circumstances.The general contractor for this projec… Read more

  • Updated

The Wisconsin Department of Transportation (WisDOT) WIS 144 culvert replacement project team will close the roadway just south of Washington County K on Tuesday August 25th between 7 a.m. and 4 p.m. The closure will impact both directions of traffic. Read more

  • Updated

WAUKESHA, WI – Construction begins this week (week of August 10) on a Waukesha County Public Works project to rehabilitate the CTH ES bridge over the Fox River. The bridge is located approximately a half-mile east of the CTH ES intersection with CTH NN on the east side of the Village of Mukw… Read more

The Highway 60 construction project affecting both Washington and Ozaukee counties has made significant progress. The project involves a new roundabout being constructed at the intersection of highways 60 and Y and is taking place on Highway 60 from Eagle Drive in Washington County to Highwa… Read more

  • Updated

WEST BEND — River Road will be closed to through traffic between Highway NN and Rusco Drive, starting Wednesday, Aug. 12, until approximately early October for utility work and road construction activities.In anticipation of this closure, and since Rusco Drive is part of the detour route, th… Read more

HARTFORD — The second and third phase of the Wacker Drive reconstruction project will begin next week and will take up to the end of October or mid-November for completion.These two phases include the removal and replacement of the Wacker Drive bridge (a Wisconsin Department of Transportatio… Read more

  • Updated

County Trunk Highway (CTH) M / Pioneer Road, from Country Aire Drive to Wasaukee Road / CTH C, is scheduled to be closed on Wednesday, August 5, 2020 and Thursday, August 6, 2020 as the Washington County Highway Department replaces a cross‐road culvert. The project location is on the border … Read more

  • Updated

WAUKESHA, WI – Waukesha County Public Works is planning to replace the culvert structure on County Highway Y at Pilak Creek Tributary in the City of Muskego. The project site is located on CTH Y just south of Pioneer Drive. Construction is anticipated to begin on September 8, 2020, and conti… Read more

  • Updated

WAUKESHA, WI – On behalf of Union Pacific Railroad, Waukesha County Public Works is announcing an upcoming closure to a Waukesha County Highway. Union Pacific Railroad has scheduled the replacement of the railroad bridge over County Trunk Highway P (Brown Street) in the Town of Oconomowoc. T… Read more

  • Updated

TOWN OF GENESEE — Contractors for the state Department of Transportation are slated to begin resurfacing work on Highway 83 this week in the Town of Genesee.The resurfacing of the roadway between Highway 59 and Perkins Road was tentatively slated to begin on Wednesday.Highway 83 will be open… Read more

  • Updated

WAUKESHA — The Wisconsin Department of Transportation is notifying the public of bridge maintenance that will begin Monday on County Road SS (Prospect Avenue) over Interstate 94.Crews will begin repairing retaining walls, roadway sections approaching the bridge, barrier wall and drainage imp… Read more

  • Updated

VILLAGE OF WAUKESHA — If you’ve been hoping to see some roads in the village patched and resealed, you’re in luck.Trustees are currently seeking bids for crack filling and blacktop sealing on more two dozen roads.Roads slated for seal coating with black boiler slag include: Arlo Drive, Coppe… Read more

  • Updated

The Canadian National railroad crossing on County Highway Q in Colgate (Village of Richfield and Town of Lisbon) will be CLOSED TO TRAFFIC as it is reconstructed. The project is scheduled to begin on Monday, July 20th and be completed by Saturday, July 26th. The crossing is approximately 3 m… Read more

  • Updated

TOWN OF GENESEE — The Wisconsin Department of Transportation will be conducting a few road closures starting Wednesday along Highway 83 in the Town of Genesee.The planned work will go from Highway 59 to Perkins Road.The improvements made will include asphalt improvement, curb and gutter and … Read more

The Washington County Highway Department’s County Trunk Highway U paving project is underway. Payne & Dolan, Inc. is pulverizing the roadway from Turtle Road to Saddle Drive, north of Hartford and anticipates finishing today. Read more

  • Updated

RICHFIELD — The paving on Hubertus Road from Hillside Road east to Mayfield Road has been completed. On Wednesday, contractors moved over to Elmwood Road. One travel lane on Elmwood Road has also been repaved so far. Read more

WAUKESHA — Due to the weather pattern this week, the North Street closure has been changed to Friday instead of Thursday this week.North Street, from Barstow Street to Brook Street, will close, which will be the last planned complete closure of North Street for the skywalk installation at th… Read more

  • Updated

Reconstruction of County Trunk Highway FD / Pioneer Road from State Trunk Highway 175 to I‐41 is nearing completion. Contractors are currently working on shouldering, signage, and landscaping. The roadway is tentatively scheduled to be completed and opened to regular traffic by 9:00 a.m. on … Read more

  • Updated

The Wisconsin Department of Transportation (WisDOT) I-94 project team will get underway with a joint repair project in Waukesha County. Work will get underway on June 22nd and will be done by mid-August. Read more

  • Updated

The Washington County Highway Department will be chip sealing three roadways with work scheduled to begin on Monday, June 8, 2020 and be completed by Tuesday, June 9, 2020. The schedule is dependent on weather and other factors. Read more

  • Updated

The Wisconsin Department of Transportation (WisDOT) WIS 83 project team will get underway with the bridge deck replacement over WIS 16 in Waukesha County. Work will get underway on May 26th and will be done by early fall. Read more

(WAUKESHA, WI) – Waukesha County Department of Public Works will begin Stage 1 reconstruction activities on County Trunk Highway (CTH) M from Calhoun Road to 124th Street in the City of Brookfield and Village of Elm Grove. Construction is anticipated to begin on May 18, 2020 and continue thr… Read more

  • Updated

JACKSON — Starting this week Highway 60 from Eagle Drive in Washington County to Highway 181 in Ozaukee County is closed. A new roundabout will be constructed at the intersection of highways 60 and Y. The project will began Monday and is scheduled to be completed in late September. Read more

The Wisconsin Department of Transportation (WisDOT) will begin work on a safety improvement project on Monday April 20th. Work will take place at various locations between Oakland Avenue and North Shore Drive. The project is expected to be complete in late Summer 2020. Read more

County Trunk Highway (CTH) D, from CTH W to Aurora Road, in the Town of Wayne (east of Kohlsville) will be closed on Monday, April 20th between the hours of 6:00 a.m. and 5:00 p.m. as the Washington County Highway Department replaces a cross‐road culvert. Read more

  • Updated

CEDARBURG — In late April, the Wisconsin Department of Transportation (WisDOT) is scheduled to begin rehabilitation and resurfacing work along WIS 60, from Eagle Drive to WIS 181, in Ozaukee and Washington counties. Prior to work starting, the community is invited to attend a construction ki… Read more

WAUKESHA – The Waukesha County Department of Public Works along with engineering consultants Graef-USA will host a public information meeting for the project to rehabilitate/ replace the pavement along Moorland Road in the city of Brookfield. Read more

  • Updated

The Wisconsin Department of Transportation (WisDOT) is sharing information to alert motorist of a closure of WIS 33 for six days beginning Monday October 28th. Work at the crossing will require a full roadway closure for the duration of the project. The detour route will use WIS 175 to Washi… Read more

  • Updated

The Washington County Highway Department will be reconstructing Pioneer Road between State Highway 175 and Richfield Parkway on the borders of the Village of Richfield and Town of Polk in 2020. After the project is completed, a jurisdictional transfer of the newly built roadway and County Hi… Read more

  • Updated

A high friction surface treatment was applied last week on the curves of County Highway H between Oak Dr and Kettle Moraine Dr in the Town of Kewaskum. This segment of roadway received a final sweeping today and is scheduled for road line painting yet this evening under closed conditions. Th… Read more